86% of the first phase of the Mass Rapid Transit (MRT) Sungai Buloh - Kajang (SBK Line or MRT Line 1) has been completed, with trial runs to start in October.

Mass Rapid Transit Corp Sdn Bhd (MRT Corp) Chief Executive Officer, Datum Shahril Mokhtar, stated that it is currently undertaking the mechanical and electrical system works of Phase 1 of the project, on track to meet its targeted completion by end of 2016.

On the other hand, Phase 2 of the SBK Line, which is the MRT Sungai Buloh - Serdang - Putrajaya line (SSP Line or MRT Line 2), is also progressing as per scheduled with the contract award of 21 work packages so far.

At the moment, land clearing and utilities piloting works have already begun in several locations of the second line, which comprises of the underground and southern elevated segments.

Phase 2 of the SBK Line is expected to be ready for operations by July 2017.



(Reference: http://www.theedgeproperty.com.my/content/829195/phase-1-mrt-line-1-undergoing-mechanical-testing-86-complete)

SHARE THIS TOPIC

Chinese ad 4621 326x150 01

P  2c3e50 small

Good addition to increase accessibility. 

Signature 28 logo  custom  small

How is the charges for the park and ride facility? monthly parking charges or daily?

Img thing small

Oh yes, I would very much like to know how much is multi-storey carpark at the MRT station if its for a full day?

65648440 2406793556070448 9165628430648082432 o small

@admin_ps thanks for sharing